Balmoral Baths and Jetty Refurbishment

Monday 6 March – Friday 7 April 2017 In progress


Council’s contractor HDSA Group will be undertaking refurbishment works on Balmoral Baths and Jetty, Mosman.

The works are programmed to be completed by 7 April 2017, weather permitting.Sections of the bathing and jetty structure will be closed for Public Safety.

[Update] The Jetty section is scheduled to be reopened for public use on 29 March 2017.

To facilitate the refurbishment works, a part of the shark net has been removed. The shark nets will be reinstated by 7 April 2017.

Council requests your cooperation to comply with on-site signage and directions.Should you require further information, please do not hesitate to contact Council's Project Engineer, Kent Tanaka on 9978 4044.


Posted 2017-03-02 · Last modified 2017-03-28 · Works: Seawalls, Baths & Jetties · Share Facebook Twitter Email