Brady Street - Road Resurfacing

Monday 7 April – Tuesday 8 April 2014 Completed


I wish to advise that Council’s contractor Ozpave will be undertaking road resurfacing works at Brady Street. Works are programmed to start on Monday 7 April 2014 weather permitting. These works are estimated to be completed overnight. Traffic control will be in effect from Monday 7 April 2014. Some sections of On Street Parking will be suspended during the works and access to some sections of the road will be restricted to residents only. At times the road will be closed when it is considered unsafe for vehicles to enter but Emergency access will be maintained at all times. Please ensure that your vehicles are NOT parked within the works area for the duration of works. The works area will be clearly marked with signage. The works are expected to affect Brady Street’s intersection with Military Road through to the pedestrian crossing near Reservoir Park.

Posted 2014-04-01 · Last modified 2019-04-22 · Works: Roads, Traffic & Cycling Paths · Share Facebook Twitter Email