Queen Street, Between Raglan Street and Bradleys Head Road

Monday 11 July – Monday 18 July 2016 Completed


Stateline Asphalt Pty Ltd will be undertaking road rehabilitation works on Queen Street, Mosman. The works are programmed to commence on 11/07/2016 and will take approximately six days to complete, weather permitting.

The work site is located between Bradleys Head Road and Reglan Street. Traffic and Pedestrian Control will be in place and parking will be suspended during the course of the works.

Sections of the road and footpath will be closed when it is considered unsafe for vehicle or pedestrian movements, however; emergency access will be provided at all times.

Please ensure that your vehicles are NOT parked on Queen Street for the duration of the works. Council requests your cooperation to comply with the temporary traffic control measures.


Posted 2016-07-05 · Last modified 2016-07-08 · Works: Roads, Traffic & Cycling Paths · Share Facebook Twitter Email

QR code