Project overview: The project involves the construction of a new pavilion and various landscaping improvements at the Middle Head Oval Precinct. The works incorporate several environmental features, including solar panels, a naturally ventilated design and rainwater harvesting. The works are comprised of:
- Modern pavilion
- Accessible pathways
- Tranquil rain garden
- Refreshed public toilets
- Lush and vibrant trees and plants
- Outdoor BBQ
Stages:
- Stage 1 Site mobilisation, demolition and foundations
- Stage 2 Main building structure, structural steel and roof
- Stage 3 Internal finishes and building fit out
- Stage 4 landscaping and external pathways
- Stage 5 final commissioning, testing and handover
Temporary facilities: Temporary public toilets will be available along the southwestern edge of Middle Head Oval.