Electrical works will commence on Monday 3rd February 2025 and will progress in 3 stages.
Stage 1
Works consist of bring cable from the existing substation on Harbour Street through existing
conduits over to the Ausgrid Substation boundary at the corner of Harbour Street and Nathan Lane.
These works are programmed to commence Monday 3rd February 2025 with an intended duration of
2 days.
Stage 2
Works consist of localised pot holing down Nathan Lane to the southern side of the footpath
followed by trenching and laying of pipe and conduit. These works will follow on from Stage 1
intended to commence Wednesday 5th February 2025 for an intended period of 4 days.
Stage 3
These works consist of trenching across Vista Street to the development side of the road where
conduit and cables will be installed. These works will follow on from Stage 2 intended to commence
Monday 10th February 2025 with an intended duration of 4 days.