Council’s Contractor, Lloyd Constructions will be undertaking rock cutting stabilisation works outside no 65 Avenue Road, Mosman. The work is scheduled to commence the week of Monday 19 October 2020 and estimated to be completed by Monday 9 November 2020, weather permitting. Standard working hours will be from 7:00am to 6:00 pm, Monday to Friday and Saturday 8am-1pm. Traffic and pedestrian control will be in effect and parking will be suspended at selected areas during the works. Please ensure that your vehicles are NOT parked within the ‘Work Zone’ areas and Council requests your cooperation to comply with the temporary traffic control measures Council has advised the Contractor to minimise possible noise disturbance. However, due to the type of machinery used for these works, some noise impacts are unavoidable. For further information please contact David Woodley 9978 4083.

Posted 2020-09-23. Last Modified 2020-09-23